Pine Flat Hydropower: Unit 4

Overview

We are dedicated to improving reliability of the electrical grid in the Valley by adding local generation capacity. The Jeff L. Taylor Pine Flat Power Plant has continued to provide a reliable carbon-free supply of energy since 1984, and with the addition of Unit 4 will provide a renewable supply of energy for California’s future growth.

Funding is needed to support the addition of a fourth hydroelectric generating unit at the Pine Flat Powerhouse to expand renewable energy sources in California’s Central Valley.

Click HERE for Unit 4 Backgrounder.

UNIT 4 IMPROVES AND EXPANDS RELIABILITY OF CLEAN & RENEWABLE ENERGY

  • The smaller Unit 4 will capture water flows available at the power plant during low-level flows. Existing units need high flows to generate power, meaning low-level flows are not currently utilized for energy generation.
  • The annual energy generation supports Renewable Portfolio Standard needs of key CA water infrastructure conveyance projects
  • At 6 MW capacity it is considered renewable energy in California
  • No environmental or recreation impacts expected
  • No change to existing water hydraulics

UNIT 4 PROJECT NEED & STATUS

FUNDING NEED: $15.6 million
TIMELINE: January 2022 – January 2024
STATUS: Initial conceptual design completed. Permitting & FERC licensing process in progress.